Laycan: laydays and cancelling

Laycan is short for laydays and cancelling. It is the window of dates in which the ship must arrive at the load port, ready to load. Arrive after it and the charterer may cancel.

Aerial view of a bulk carrier with closed hatch covers and a tug alongside
A bulk carrier with a tug alongside. Photo: iStock.
Laycan 10 to 15 December678910111213141516171819Arrives early: waits.Laytime starts on the 10th.Arrives ready in the window:charter proceeds.Arrives after the 15th:charterer may cancel.
The first date is the earliest laytime can start. The second is the cancelling date.

The two dates

The first layday is the earliest date the charterer has to accept the ship. If she arrives sooner she waits, and laytime does not start until that date unless the charterer agrees.

The cancelling date is the latest. If the ship has not arrived and given a valid notice of readiness by then, the charterer has the option to cancel the charter. It is an option, not an automatic end: the charterer can also keep the ship, often after renegotiating.

Why the window matters to each side

How wide should a laycan be?

Five to ten days is common for dry bulk, narrower for tankers. A tight window gives the charterer certainty and costs the owner flexibility, which shows up in the freight rate. A cargo posted with a realistic window attracts more offers.

If the ship is going to be late

Many charter parties have an interpellation clause. The owner tells the charterer the new expected date and the charterer must say, within a set time, whether they will cancel. This stops the ship steaming for days towards a cargo that has already gone elsewhere.

Laycan in an offer

An owner can offer a narrower window inside the one the charterer posted, for example 12 to 14 December against 10 to 15. Check that the offered dates still fit your cargo before accepting.